How to Specify Salt Spray Test Hours on a Drawing
QUICK ANSWER
Write the test standard, the duration and the acceptance criteria as three separate lines, then record which sample the result is compared with. There is no default number of hours, because the same finish behaves differently on different substrates. Where a value is not decided yet, keep it TBC and settle it before the first lot.
Why there is no default number of hours
A salt spray result describes one finish on one substrate under one set of conditions. Copy a number from another project and it may pass on paper while the part still fails in service.
The duration people quote usually comes from a customer standard, a market requirement or an earlier part. None of those transfer automatically to a new casting, coating or environment.
So the useful question is not "how many hours do you recommend", but "which standard, which duration and which failure counts as a reject for this part".
Fix the standard before the hours
Name the standard and the exposure type. ISO 9227 is the reference our customers usually cite, and the standard itself fixes the salt solution, the temperature and the collection rate.
Neutral salt spray is the common case for decorative hardware. Other variants exist for specific service conditions, and choosing one changes what the result means.
If your market or your customer already names a standard, send it with the drawing. We confirm whether our process is evaluated that way rather than assuming a familiar route.
Hours and acceptance criteria are separate lines
The duration says how long the sample is exposed. The acceptance criterion says what may be seen afterwards, such as whether white corrosion on edges is allowed and how much area may change.
Without a criterion, a laboratory report is just a photograph. Two buyers can look at the same panel and reach opposite conclusions, which is what makes disputes expensive.
State where the part is evaluated: the visible face, the edge, or the threaded area. A criterion written for a flat panel does not read the same way on a cast edge.
Where the test sits in the order
There is a difference between a type test, run once to approve a finish, and a check repeated on production lots. Say which one you need, because the sampling and the cost differ.
The sample itself matters too. A flat test panel and a real casting with edges, holes and threads do not corrode the same way, and the part is what the customer receives.
Our outgoing inspection follows AQL 1.0 for the agreed characteristics. Salt spray is added to that plan only where the specification asks for it.
What the substrate and the finish do to the result
A plated layer on a zinc casting, a powder film on aluminium and a PVD film behave differently once the surface is damaged. Some finishes protect by barrier, others by sacrifice.
Film thickness and edge coverage matter more than the name of the process. A well-covered edge on a modest finish can outlast a premium finish with a thin edge.
That is why the same hours can pass on one part and fail on another from the same drawing. The test measures the pair of substrate and finish, not a universal grade.
Writing it into the specification
Put four items on one line: the standard, the exposure type, the duration and the acceptance criterion. Then add the sample, for example a production part rather than a test panel.
If the duration still depends on your customer or your market, write TBC and the date you expect the answer. It is clearer than an invented figure that nobody can defend later.
Keep the agreed reference part with the paperwork. When a new lot is compared, the judgement goes back to that part, not to memory or to a photograph on a phone.
- Standard and exposure type, for example ISO 9227 neutral salt spray.
- Duration in hours, or TBC with the date it will be fixed.
- Acceptance criterion by area, and the sample it is judged on.
Reading a salt spray report
Check the method and the duration first, then the sample description. A report that does not say which part or which finish was tested cannot support a decision on your order.
Then compare the result with the criterion, not with the panel. Photographs help, but the written judgement of white or red corrosion by area is what the lot is accepted on.
If a report is older than the process you run now, ask for a fresh one. A change of powder lot, plating chemistry or pre-treatment can move the result without any drawing change.
What a salt spray test costs in time
The test itself takes as long as the duration you specify, and that sits on top of production. A long duration therefore pushes a delivery date even when the parts are already finished.
Sample preparation adds a day or two: cleaning, masking and labelling before the chamber. Rushing that step makes the result harder to defend, not faster to accept.
For a first order, plan the test into the approval stage rather than after it. Added later, it usually means a second sample round and a later shipment.
Mistakes that make a salt spray clause useless
The first mistake is writing hours and nothing else. Without a standard, the number cannot be reproduced, and two suppliers can both claim to meet it with different tests.
The second is leaving out the acceptance criterion, so the report shows a panel and lets the reader decide. The third is testing only a flat panel when the delivered part has edges and threads.
The fourth is attaching an old report to a new order. If the powder lot, the plating chemistry or the pre-treatment changed, the report describes a part you no longer buy.
Example wording you can adapt
A workable clause reads: salt spray to ISO 9227, neutral, for the duration stated in the purchase specification, judged on the visible face against the approved sample.
The duration stays open until you fill it in, and the clause still works. Nobody has to guess a figure, and nothing is hidden in a footnote.
If your customer insists on a figure, add it as a stated value rather than as a default, and name who set it. That keeps the responsibility visible.
Send the clause with the enquiry and ask us to confirm feasibility. A finish that cannot reach the figure is better discussed before tooling than after the first lot.
Questions from Buyers
It depends on the market, the part and the finish, so we do not publish a default. Tell us where the product is sold and how long it must last, and we help set a figure you can defend.
Send Your Drawing, Get a Written Quote in 24 Hours
A drawing, a sample or a target price is enough to start. Tooling in 25 days, samples in 7 days.